Invest on equipments to enhance construction progress of RCC in Dong Nai 4 hydroelectricity plant
In order to enhance construction progress and to ensure RCC quality of Dong Nai 4 hydropower project. In the past time, CC47 has invested more than 2 billion VND for purchasing special equipment of the sweeper & sucker truck, model MS6RS produced by Hyundai Korea in 2009: its purpose is cleaning and sucking water on the RCC surface.

The company is making procedure & documents and quickly put the truck into operation for RCC contruction work in Dong Nai 4 hydropower project.


Annual report 2011
*/ View or Download: Here
Annual report 2010
*/ View or Download: Here
Tra Co Reservoir Works
Location of works: | Bac Ai District, Ninh Thuan Province | |
Length of dam as per center line: | 153m | |
Crest height of main earth dam: | 26.7m | |
Main volume of works: | ||
+ Rock & soil excavating: | 122,365m3 | |
+ Rock & soil filling: | 83,344m3 | |
+ CVC works: | 15,965m3 | |
Duration of works: | ||
+ Commencement: | The fourth quarter of 2006 | |
+ Completion: | The fourth quarter of 2009 |