| Location of works: | Cam Phuoc Tay Commune, Cam Lam District, Khanh Hoa Province, Vietnam | |
| Length of Dam: | 950m | |
| Height of Crest: | 58m | |
| Main volume of works: | ||
| + Rock & soil excavation: | 1.350.742m3 | |
| + Rock & soil fill: | 2.633.860m3 | |
| + CVC works: | 22.145m3 | |
| Works duration: | ||
| + Commencement: | 01/01/2010 | |
| + Completion: | 2014 | |