C47

  • Tiếng Việt
  • English
  • Home
  • Introduction
    • General Introduction
    • Download Introduction
    • Achievements and Awards
    • Organizational Chart
    • Communist Party & Unions
    • Quality Policy of Company
  • Works & Projects
    • Hydraulic Works
    • Hydroelectric Works
    • Civil & Industrial construction works
    • Video Clips
  • Investment
    • Construction & Services
    • Equipments & Technology
    • Other Sectors
  • News & Events
    • News
    • Science – Technology
    • Reportage – Special subject
    • Economy – Social Affairs
  • Shareholder Relations
    • Shareholder information
    • Financial Report
    • Annual Report
    • Announcement
    • Shareholder Meeting
    • Minutes & Resolutions
    • Management reports
    • Charters & Regulation
  • Information
    • Bidding
    • Recruitment
    • On-going projects undertaken by C47
  • Contacts
C47 > Articles by: admin_c47

31/07/2021 by

CC47 makes an entire investment in developing a professional model of labor supply, training, export

Along with the main production and business lines, Construction Joint Stock Company 47 places a special emphasis on education, vocational training, and human resource training, which have potential of global integration. The Binh Dinh Labor Supply Single Share – holder Limited Company, established with 100% investment from CC47, will associate with Binh Dinh Labor Export & Tourism Vocational Training Center, Binh Dinh Consulting Center of Abroad Study, Youth Center of Foreign Language & Information to constitute a complete system chain of labor supply and training. The center ensures professional human resources for the localities, enterprises and other countries. Since 2017, the labor export market to Japan has been identified as a potential in Binh Dinh province, attracting a number of large-scale Japanese companies to visit for market research, investment, and labor recruitment. Throughout our operation, we have received high praise from Japanese trade unions, and we have become a strategic partner in training Japanese language and vocational skills for laborers to export to the Japanese market. As a reputable and dependable link for many domestic workers and foreign businesses, workers are “placed” in the right place, and businesses “hire” the right people. The dispatched workers have high incomes, which helps to improve family life and build the local economy.

CC47 was the first enterprise to be licensed by the Japan Welding Association to train skilled welding workers,

Binh Dinh Tourism and Labor Export (Area 2- Ghenh Rang Ward – Quy Nhon City) is constantly upgraded to create the best learning environment for students to meet the training and teaching needs of Binh Dinh Vocational Education and Training Center.

The picture of the Training Center

Land use area: nearly 10,000 m2, is a closed complex training area in which:

+ Office area: 195 m2 (02 floors) including offices of the Board of Directors, Organization-Administration, Accounting, Training, Teachers, and Meeting rooms.

+ Lecture hall: 220 m2 (1 floor) including 3 classrooms and 02 restrooms;

+ Dormitory area: 350 m2, (1 floor) including 10 rooms with toilet in each room; catering for 100 students on vacation.

+ Dining area: 150m2 (1 floor)

+ Garden, sports, garage about more than 9000 m2: flower garden, bonsai, mini football field…

In addition to training interns for labor export, the Center is one of Binh Dinh’s leading tourism training units, specializing in professional training and improving working skills in the fields of restaurants, hotels, and travel. Many students have been trained at the Center over the years and are now working effectively in domestic and international tourism service enterprises. It creates a model of theoretical training associated with practical practice by combining with the 4-star Hai Au Hotel under CC47, assisting students after graduation to own sufficient skills to meet the requirements of the majority of employers.

Filed Under: Investment, News, Other Sectors

30/07/2021 by

CC47 makes an entire investment to establish the brand Seagull Travel Center

Along with the Seagull Hotel brand, Seagull Travel operates under the original name of Seagull Travel Service Center, which is approved by the General Department of Tourism – Ministry of Culture, Sports and Tourism to issue an international travel business license number: 52-001/2010/TCDL–GPLHQT.

In 2013, Seagull Travel Service Center was honored to receive the top awards of the tourism industry, typically the title of “Good Management – Quality Service in the Tourism Industry for the first time – 2013”.

In order to maintain its success and position in the tourism industry, Seagull Travel Service Center expanded its scope and changed its name to Seagull Travel Service Company Limited in 2018 with a one-hundred percent investment from Construction Joint Stock Company 47.

With modern and high-quality facilities, we build a team of professional, enthusiastic, and experienced domestic and international market staff, operators, and guides.

Innovative passenger cars from 4 seats to 45 seats

 

Seagull Travel always leaves a good impression in the hearts of tourists thanks to the increasingly diverse services and improved service quality, which contributes to create a prestigious brand and a solid position in the tourism industry of Binh Dinh province.

Seagull Travel looks forward to accompanying you to the wonders and landscapes in the country and around the world, sharing success, joy as well as memorable moments with you.

Services at the Company:

Prestigious air ticketing agent of airlines Vietnam Airlines, Vietjet Air…

Sightseeing tourism;

Cultural tourism;

Thematic tourism;

Tourism combined with study tours, conferences, seminars;

Domestic and foreign tours as rewards for employees,

Tourism combined with resort;

World tour program: China, Thailand; Singapore, Malaysia, Laos, Cambodia, Korea…

Filed Under: Construction & Services, Investment, Other Sectors

27/07/2021 by

Construction Joint Stock Company 47 (CC47) witnessed a profit increase of 29.45% over the same period in 2020, exceeding the revenue plan for the first 6 months of 2021

In a consolidated financial statements of Construction Joint Stock Company 47 (HoSE: C47) in the first 6 months of 2021, total revenue reached VND 572 billion and profit after tax was VND 17.1 billion, reaching 52% of the revenue plan and 55 % profit plan in 2021.

Bac Ai Pumped-storage Hydropower Project in Ninh Thuan Province

The Covid-19 epidemic was more complicated in early 2021 compared to the same period in 2020, but thanks to the implementation of various proactive measures, such as travel reduction, personnel rotation and commitment to 3 On-site rules (on-site production – on-site dining – on-site accommodation), CC47’s main production and business activities are still running smoothly. According to the business results explanation for the first six months of 2021, which was released on July 22, 2021, profit after tax increased by 29.45 percent over the same period in 2020, while revenue increased by 3 percent. This result was achieved as a result of proactive planning and favorable construction conditions, as well as the company actively cutting costs, particularly interest expenses, resulting in lower financial costs of 28% compared to the same period.

The year of 2021 also witnessed significant price fluctuations in the construction industry’s main materials, particularly iron and steel, but Mr. Duong Minh Quang, the company’s General Director, stated that CC47 is not at risk due to rising prices. C47’s contracts under cooperation with reputable investors, have an adequate allocation of capital, and a permission to adjust prices when the government changes policies, when wages, material prices, and fuel prices fluctuate. On the other hand, in order to promote economic development during the pandemic, the State is currently increasing public investment and speeding up the implementation of key hydropower, irrigation, and other infrastructure projects. This is also the opportunity and strength of CC47 to participate in bidding for projects in the near run.

The main dam of Dong Mit reservoir in Binh Dinh province

Package 12.01 (DNE-D1): The main construction and architecture of the Da Nhim Hydropower Plant Expansion Project with a scale of 1 newly installed unit, capacity of 80MW are executed by CC47. The Da Nhim Hydropower Plant Expansion Project’s Headrace Tunnel has been recently inspected and accepted by the Grassroots Acceptance Council. The Acceptance Council agreed to operate the tunnel on July 21, 2021, six days ahead of schedule, after inspecting the entire length of 4,908.57m from the Intake to the Valve house.

Acceptance of Headrace Tunnel under Da Nhim Hydropower Plant Expansion Project

CC47 has also completed all the work items under the contract of Package 20: Main dam and auxiliary dam No. 1 Tan My Irrigation System Project in Ninh Thuan province (including drilling, total construction site of the right bank of the Cai River, overflow mechanics, deep outlet, operating electricity, monitoring system of Song Cai and auxiliary dam 1). In this project, CC47 is the leading unit of the contractor consortium. Currently, CC47 is completing the remaining construction works (Digging of scour pool in phase 2, operating electrical systems, finishing upstream and downstream surfaces, erecting dam face railings…). It is expected to be officially completed at the end of August 2021 and handed over to the Investor for use in September 2021.

The main dam of Tan My Irrigation System in Ninh Thuan Province

The expanded Hoa Binh Hydropower Project is also progressing at the request of the investor, has completed the experimental blasting and is preparing for the construction of the main and auxiliary tunnels.

Drilling and blasting to test tunnels – Hoa Binh Hydropower Plant Extension Project

CC47 has constructed many projects such as Dinh Binh Reservoir – Binh Dinh Province (850 billion VND), Nuoc Trong Reservoir – Quang Ngai Province (1,052 billion VND), Dong Nai 4 Hydropower Plant – Dak Nong Province (2,600 billion VND), Thuong Kontum Hydropower Plant – Kon Tum Province (1,700 billion VND), Trung Son Hydropower Plant – Thanh Hoa Province (2,959 billion VND). In addition, the Company is operating in the field of hotels and restaurants in Quy Nhon such as Hai Au Seagull hotel (4 stars), Hai Au Bien Cuong Hotel (3 stars), Domestic and International travel, Labor export. Hai Au Hotel is coordinating with the province to become a welcoming place for guests returning to their hometown.

Regading the business plan for the period 2021-2025, CC47 will continue to maintain the traditional business lines as general contractor for irrigation projects, large hydropower projects, headrace tunnels, etc. In addition, with years of experience, the Company intends to challenge in the construction of wind and gas power projects, participate in the construction of metro tunnels using TBM technology, construction of traffic infrastructure and industrial park infrastructure, expanding key markets serving Southeast and Southwest regions.

Filed Under: News

27/07/2021 by

The Headrace tunnel of Da Nhim Expansion Project is completed ahead of schedule

The Grassroots Acceptance Council inspected and approved the Headrace Tunnel for the Da Nhim Hydropower Plant Expansion project on July 20, 2021. The Acceptance Council agreed to put in into operation on July 21, 2021, six days ahead of schedule, after inspecting the entire length of 4,908.57m from the Intake to the Valve House.

The inspection team

Regarding members of the Grassroots Acceptance Council, there were leaders of Da Nhim Hydropower Plant Expansion Project Management Board (representative of Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company as the Investor), Supervision Consultant (Nippon Koei – PECC3 – Nippon Koei Vietnam), Design Consultant (Power Engineering Construction Joint Stock Company 2), Construction Contractor (Construction Joint Stock Company 47) and Hydro-mechanical Contractor (NARIME – COMA Consortium).

Headrace Tunnel under Da Nhim Hydropower Plant Expansion Project with a total length of 4,908.57m is constructed by TBM (Tunnel Boring Machine) and partly by Drilling and Blasting method. Tunneling work with TBM started on April 1, 2017 with a diameter of 3.9m. On March 23, 2019, when 3,739.51m had been drilled, the tunnel slippage occurred when the TBM passed through a weak geological area. Although the Owner, Consultant and Contractor have made efforts to reinforce and fix the tunnel but the TBM equipment cannot continue to dig the remaining tunnel.

The tunnel section is constructed by TBM at the location of 2,750m

Following approval from the Ministry of Industry and Trade to change the TBM construction plan to drilling and blasting for the remaining 929.05m tunnel, the Construction Contractor resumed work on February 6, 2020, and completed the tunnel on December 14, 2020. After about 6 months of focusing on covering and reinforcing the tunnel at sections with weak geology and overall hygiene, the entire tunnel was ready for acceptance and use on July 20, 2021.

The tunnel section is covered with concrete

Mr. Luu The Bieu – Deputy Director of the Project Management Board – did not hide his emotion when speaking at the acceptance meeting to put the tunnel into use on the same day: “After a difficult time of construction, the Headrace tunnel is ready for water filling. The Da Nhim expansion project is now officially completed. What makes me proud of is the tunnel quality and the construction safety for laborers and equipment”.

To ensure the progress of putting unit H5 of 80 MW under the Da Nhim expansion project into operation in the third quarter of 2021, Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company (DHD) launched an emulation on 16th June 2020. The emulation aims at catching the schedule of filling the tunnel on July 26, 2021 and completing the 72-hour challenge of unit H5 with a capacity of 80MW on August 8, 2021. The completion of the Headrace Tunnel of Da Nhim Hydropower Plant Expansion Project was 6 days ahead of schedule.

The Headrace Tunnel Item under Da Nhim Hydropower Plant Expansion Project is completed ahead of schedule and is considered a crucial basis to put Unit H5 into operation for resource efficiency. Up to now, the inspection of unit H5 after 2.5 years of operation with a capacity of 45MW is being carried out urgently, completing the final items to operate with a capacity of 80MW.

Unit H5 with a capacity of 80MW will increase the total capacity of Da Nhim hydropower plant to 240MW, contributing to additional power sources, especially at off-peak hours for the national power grid. As a multi-purpose hydropower plant, Da Nhim hydroelectricity annually provides more than 1.1 billion kWh for socio-economic development; At the same time, it is an abundant water source for agricultural production in the delta of Ninh Thuan province.

Filed Under: News, News & Events

21/07/2021 by

C47 has basically completed 2 large-scale projects, implemented 3 new bidding packages for the first 6 months of 2021

Construction Joint Stock Company 47 (CC47) is maintaining a good growth rate and meeting the set business targets thanks to a detailed strategy and strong determination. CC47 has currently completed all work items under the contract of two projects, the Da Nhim Hydropower Plant Expansion Project and the Tan My Irrigation System Project, and is still constructing major projects, including three new bidding packages in Binh Dinh and Lam Dong in 2021, as well as the expanded Hoa Binh Hydropower Package, which began earlier this year. The first six months of the year are expected to generate more than half of the year’s revenue and profit.

RCC reservoir – Tan My Irrigation system

In the Package 12.01 (DNE-D1), Construction Joint Stock Company 47 is responsible for construction  and architecture of the Da Nhim Hydropower Plant Expansion Project, which has a scale of 1 newly installed unit with capacity of 80MW. Until now, all work items specified in the contract have been completed. C47 is executing the remaining construction works to ensure the completion of Headrace Tunnel’s water filling on July 26, 2021 and try out 72-hour operation of unit H5 on August 8, 2021.

Headrace Tunnel constructed by TBM technology – Da Nhim Expanded Hydropower Plant Project
Penstocks – Da Nhim hydropower Plant Expansion Project
At the end of the Penstocks comes the Hydropower Plant

C47 has also completed all the work items under the contract of Package 20: Main dam and auxiliary dam No. 1 Tan My Irrigation System Project, Ninh Thuan province (including grouting, total construction site of the right bank of the Cai River, mechanical work, deep outlet, electrical operation, systematic control of the Cai River focal dam and auxiliary dam 1). In this project, C47 is the leading unit of the contractor consortium. Currently, C47 is executing the remaining construction works (Digging of scour holes in phase 2, operating electrical systems, finishing upstream and downstream surfaces, erecting dam face railings…). It is expected to be officially completed at the end of August 2021 in order to be handed over to the Investor for operation in September 2021.

Main dam of Tan My Irrigation System
Perspective picture of Hoa Binh Hydropower Plant expansion project
CC47 construction process takes place in Hoa Binh Hydropower Plant Expansion Project

The contract value of the Dong Mit Hydropower Plant Project, with a capacity of 7MW in An Trung commune, An Lao district, Binh Dinh province, is VND 29 billion. The total contract value for Package 7: C1-LAMDONG-W1 (Plot 1: Construction) of Sub-Project 02: Repairing and improving dam safety (WB8) in Lam Dong province is 106 billion dong.

Adhering to the motto “Quality and Time assurance is the brand”, CC47 aims to maintain business efficiency and safety, proactively respond to many scenarios of the Covid-19 pandemic. The Company has achieved basic business targets in the first 6 months, is continuing to expand the market and fulfil the annual business goal as set out. In 2021, CC47 is expected to win many new bidding packages with a total value of more than one trillion dong, ensuring the revenue for the following years.

Regarding the current contracts, CC47 cooperated with prestigious Investors, distributed adequate capital, and is granted a right to adjust prices when there is price fluctuation in labor salary, material and fuel cost, therefore risks of price surge disappear. On the other hand, in order to encourage economic development during the pandemic, the State is currently increasing public investment and accelerating the implementation of key projects on hydropower, irrigation and other infrastructure. This is also the opportunity and strength of CC47 to participate in bidding for projects in the future.

In terms of the business plan for the period 2021-2025, CC47 will continue to maintain the traditional business lines as general contractor for irrigation projects, large hydropower projects, headrace tunnels, etc. In addition, the Company takes advantage of construction experience to step into the construction fields of wind power, metro tunnels, traffic infrastructure, industrial zones’ infrastructure in Southeast and Southwest regions.

Filed Under: News

  • « Previous Page
  • 1
  • …
  • 19
  • 20
  • 21
  • 22
  • 23
  • …
  • 61
  • Next Page »

SUPPLIERS & CONTRACTORS PORTAL

The C47 brand has now become a quality guarantee for world-class buildings. Click on the link to join Supply Chain C47

Submit/RegisterFeedback
0256.3522166
HOTLINE

VIDEO

Công ty Cổ phần Xây dựng 47

Construction Joint Stock Company 47

Kỷ niệm 45 năm thành lập Công ty Cổ phần Xây dựng 47

45th Year Anniversary for establishment of Construction Joint Stock Company 47

Music: Hát về Công ty 47 anh hùng

https://www.xaydung47.vn/wp-content/uploads/2021/03/C47_AH_FIle_Goc.mp3

RECRUITMENT

We’re looking for Assistant to Chairman

Announcement of second recruitment in 2018

Announcement of labor recruitment phase 1 in 2018

Recruitment announcement for the first phase of 2017

Announcement of labor recruitment phase 3 in 2016

COMPANY INFO

  • General Introduction
  • Achievements and Awards
  • Organizational Chart
  • Communist Party & Unions
  • Quality Policy of Company

INVESTOR RELATIONS

  • Information
  • Financial Report
  • Annual Report
  • Announcement
  • Minutes & Resolutions

CONTACTS

Main Office Building C47:
  • No 8 Bien Cuong - Quy Nhon Nam - Gia Lai
  • 0256.3522166 - 0256.3522931
  • c47@xaydung47.vn

C47

Copyright © 2025 Công ty Cổ phần Xây dựng 47
Developed by Vũ Phong Energy Group