C47

  • Tiếng Việt
  • English
  • Home
  • Introduction
    • General Introduction
    • Vision – Mission – Core values
    • Download Introduction
    • Achievements and Awards
    • Organizational Chart
    • Communist Party & Unions
    • Quality Policy of Company
  • Works & Projects
    • Hydraulic Works
    • Hydroelectric Works
    • Civil & Industrial construction works
    • Video Clips
  • Investment
    • Construction & Services
    • Equipments & Technology
    • Other Sectors
  • News & Events
    • News
    • Science – Technology
    • Reportage – Special subject
    • Economy – Social Affairs
  • Shareholder Relations
    • Shareholder information
    • Financial Report
    • Annual Report
    • Announcement
    • Shareholder Meeting
    • Minutes & Resolutions
    • Management reports
    • Charters & Regulation
  • Information
    • Bidding
    • Recruitment
    • On-going projects undertaken by C47
  • Contacts
C47 > News & Events > News > The Headrace tunnel of Da Nhim Expansion Project is completed ahead of schedule

27/07/2021 by

The Headrace tunnel of Da Nhim Expansion Project is completed ahead of schedule

The Grassroots Acceptance Council inspected and approved the Headrace Tunnel for the Da Nhim Hydropower Plant Expansion project on July 20, 2021. The Acceptance Council agreed to put in into operation on July 21, 2021, six days ahead of schedule, after inspecting the entire length of 4,908.57m from the Intake to the Valve House.

The inspection team

Regarding members of the Grassroots Acceptance Council, there were leaders of Da Nhim Hydropower Plant Expansion Project Management Board (representative of Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company as the Investor), Supervision Consultant (Nippon Koei – PECC3 – Nippon Koei Vietnam), Design Consultant (Power Engineering Construction Joint Stock Company 2), Construction Contractor (Construction Joint Stock Company 47) and Hydro-mechanical Contractor (NARIME – COMA Consortium).

Headrace Tunnel under Da Nhim Hydropower Plant Expansion Project with a total length of 4,908.57m is constructed by TBM (Tunnel Boring Machine) and partly by Drilling and Blasting method. Tunneling work with TBM started on April 1, 2017 with a diameter of 3.9m. On March 23, 2019, when 3,739.51m had been drilled, the tunnel slippage occurred when the TBM passed through a weak geological area. Although the Owner, Consultant and Contractor have made efforts to reinforce and fix the tunnel but the TBM equipment cannot continue to dig the remaining tunnel.

The tunnel section is constructed by TBM at the location of 2,750m

Following approval from the Ministry of Industry and Trade to change the TBM construction plan to drilling and blasting for the remaining 929.05m tunnel, the Construction Contractor resumed work on February 6, 2020, and completed the tunnel on December 14, 2020. After about 6 months of focusing on covering and reinforcing the tunnel at sections with weak geology and overall hygiene, the entire tunnel was ready for acceptance and use on July 20, 2021.

The tunnel section is covered with concrete

Mr. Luu The Bieu – Deputy Director of the Project Management Board – did not hide his emotion when speaking at the acceptance meeting to put the tunnel into use on the same day: “After a difficult time of construction, the Headrace tunnel is ready for water filling. The Da Nhim expansion project is now officially completed. What makes me proud of is the tunnel quality and the construction safety for laborers and equipment”.

To ensure the progress of putting unit H5 of 80 MW under the Da Nhim expansion project into operation in the third quarter of 2021, Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company (DHD) launched an emulation on 16th June 2020. The emulation aims at catching the schedule of filling the tunnel on July 26, 2021 and completing the 72-hour challenge of unit H5 with a capacity of 80MW on August 8, 2021. The completion of the Headrace Tunnel of Da Nhim Hydropower Plant Expansion Project was 6 days ahead of schedule.

The Headrace Tunnel Item under Da Nhim Hydropower Plant Expansion Project is completed ahead of schedule and is considered a crucial basis to put Unit H5 into operation for resource efficiency. Up to now, the inspection of unit H5 after 2.5 years of operation with a capacity of 45MW is being carried out urgently, completing the final items to operate with a capacity of 80MW.

Unit H5 with a capacity of 80MW will increase the total capacity of Da Nhim hydropower plant to 240MW, contributing to additional power sources, especially at off-peak hours for the national power grid. As a multi-purpose hydropower plant, Da Nhim hydroelectricity annually provides more than 1.1 billion kWh for socio-economic development; At the same time, it is an abundant water source for agricultural production in the delta of Ninh Thuan province.

Filed Under: News, News & Events

RELATED POSTS

C47 Pickleball Club Tournament: Explosive Sporting Spirit Celebrating Workers’ Month and Marking the Club’s Official Launch

C47 Pickleball Club Tournament: Explosive Sporting Spirit Celebrating Workers’ Month and Marking the Club’s Official Launch

Responding to Workers’ Month, practically celebrating the Reunification Day on April 30 and International Workers’ Day on May 1, and marking the official launch of the C47 Pickleball Club, the ...
Nam Neun 1 – CC47’s International EPC Contractor Courage from the Mega Construction Site in Laos

Nam Neun 1 – CC47’s International EPC Contractor Courage from the Mega Construction Site in Laos

There are projects that do not require elaborate introductions to leave a lasting impression. They affirm themselves through execution capability and intrinsic value. For CC47, the distinction lies not in ...
C47: Disclosure of Information on the Board of Directors’ Resolution Approving Updates to Documents Submitted to the 2026 Annual General Meeting of Shareholders

C47: Disclosure of Information on the Board of Directors’ Resolution Approving Updates to Documents Submitted to the 2026 Annual General Meeting of Shareholders

On April 4, 2026, Construction Joint Stock Company 47 (HOSE: C47) successfully held the 2026 Annual General Meeting of Shareholders at the Hall on the 11th Floor, Building 47, No ...
CC47 Present at 2 of 3 Key Power Projects in 2026, Launching Emulation Campaign Toward the 2026 Annual General Meeting of Shareholders

CC47 Present at 2 of 3 Key Power Projects in 2026, Launching Emulation Campaign Toward the 2026 Annual General Meeting of Shareholders

In the context of the upcoming 2026 Annual General Meeting of Shareholders, scheduled to be held on April 4, 2026, Construction Joint Stock Company 47 (HOSE: C47) is delivering a ...
2026 AGM: C47 Targets VND 1,800 Billion in Revenue and VND 60 Billion in Profit After Tax; Accelerating Energy Strategy in Laos

2026 AGM: C47 Targets VND 1,800 Billion in Revenue and VND 60 Billion in Profit After Tax; Accelerating Energy Strategy in Laos

Concluding the 2025 financial year with impressive results, CC47 recorded strong business performance with revenue of VND 1,666.8 billion (equivalent to 111.2% of the 2025 plan) and profit after tax ...

SUPPLIERS & CONTRACTORS PORTAL

The C47 brand has now become a quality guarantee for world-class buildings. Click on the link to join Supply Chain C47

Submit/RegisterFeedback
+84 256.3522166
HOTLINE

VIDEO

Corporate Video C47 – The 50-Year Journey (1975–2025)

Construction Joint Stock Company 47

Dự án Hành trình xanh - Tri thức số

Green Journey – Digital Knowledge

Music: Hát về Công ty 47 anh hùng

https://www.xaydung47.vn/wp-content/uploads/2021/03/C47_AH_FIle_Goc.mp3

BIDDING

Notice of Extension of Submission Deadline for Competitive Quotation Invitation – Package: Quotation for Customs Clearance Services for Import/Export Procedures into the Lao PDR at Nam Kan Border Gate

Notice of Extension of Submission Deadline for Competitive Quotation Invitation – Package: Quotation for Customs Clearance Services for Import/Export Procedures into the Lao PDR at Nam Kan Border Gate

Invitation for quotation provision of Customs Clearance Services for Import/Temporary Import – Re-export in Laos for Nam Neun 1 Hydropower Project

Invitation for quotation provision of Customs Clearance Services for Import/Temporary Import – Re-export in Laos for Nam Neun 1 Hydropower Project

COMPANY INFO

  • General Introduction
  • Achievements and Awards
  • Organizational Chart
  • Communist Party & Unions
  • Quality Policy of Company

INVESTOR RELATIONS

  • Information
  • Financial Report
  • Annual Report
  • Announcement
  • Minutes & Resolutions

CONTACTS

Main Office Building C47:
  • No 8 Bien Cuong - Quy Nhon Nam - Gia Lai
  • 0256.3522166 - 0256.3522931
  • c47@xaydung47.vn

C47

Copyright © 2026 Công ty Cổ phần Xây dựng 47
Developed by Vũ Phong Energy Group