| Location of works | :Bac Ai District, Ninh Thuan Province, Viet Nam | |
| Length of Dam | :425m | |
| Height of Dam | :33,9m | |
| Works duration: | ||
| + Rock & soil excavation | :602,394m3 | |
| + Rock & soil fill | :654,968m3 | |
| + CVC works | :2,163m3 | |
| Works duration: | ||
| + Commencement | :2004 | |
| + Completion | :2007 | |





C47