| Construction Location: | Phu Quoc Special Zone, An Giang Province | |
| Main Quantities: | ||
| + Earth excavation: | 3,150,464 m3 | |
| + Rock excavation: | 544,000 m3 | |
| + Concrete works: | 72,031 m3 | |
| + Steel works: | 3,359 tons | |
| Construction and Completion Schedule: | ||
| + Contract signed: | 10/11/2025 | |
| + Completion: | Expected on 31/03/2027 | |