| Construction location: | Hieu Liem Commune, Vinh Cuu District, Dong Nai Province | |
| Main quantities: | ||
| + Excavation of soil and rock: | 319.497 m3 | |
| + CVC concrete of all types: | 41.127 m3 | |
| Construction and completion schedule: | ||
| + Contract signed: | 03/06/2025 | |
| + Groundbreaking: | 19/08/2025 | |
| + Completion: | 31/12/2027 | |