| Location of works: | Tay Son District, Binh Dinh Province, Viet Nam | |
| Length of Dam: | 589m | |
| Height of Crest: | 15.5m | |
| Main volume of works: | ||
| + Rock & soil excavation: | 575,000m3 | |
| + Rock & soil fill: | 450,850m3 | |
| + CVC works: | 133,000m3 | |
| + RCC works: | 353,000m3 | |
| Works duration: | ||
| + Commencement: | The first quarter of 2022 | |
| + Completion: | The Third quarter of 2024 | |