| Project Location: | Canh Vinh commune, Van Canh district, Binh Dinh province | |
| Main Volume: | ||
| + Rock gabion: | Length of 3,440m with volume of 40,755m3 rubble stone | |
| + Rock and soil excavation: | 103,111m3 | |
| + Rock and soil filling: | 254,721m3 | |
| Construction Period: | ||
| + Commencement: | Quarter 3/2022 | |
| + Completion: | Quarter 1/2023 | |