| Location of site: | A Luoi District, Thua Thien – Hue Province | |
| Length of main weir: | 206.5m | |
| Height of main weir crest: | 49.5m | |
| Main volume of implementation : | ||
| + Rock & soil excavation: | 1,650,422m3 | |
| + Rock & soil fill: | 107,470m3 | |
| + CVC works: | 137,342m3 | |
| Duration of works: | ||
| + Commencement: | The fourth quarter of 2007 | |
| + Completion: | The fourth quarter of 2010 | |