C47

  • Tiếng Việt
  • English
  • Home
  • Introduction
    • General Introduction
    • Vision – Mission – Core values
    • Download Introduction
    • Achievements and Awards
    • Organizational Chart
    • Communist Party & Unions
    • Quality Policy of Company
  • Works & Projects
    • Hydraulic Works
    • Hydroelectric Works
    • Civil & Industrial construction works
    • Video Clips
  • Investment
    • Construction & Services
    • Equipments & Technology
    • Other Sectors
  • News & Events
    • News
    • Science – Technology
    • Reportage – Special subject
    • Economy – Social Affairs
  • Shareholder Relations
    • Shareholder information
    • Financial Report
    • Annual Report
    • Announcement
    • Shareholder Meeting
    • Minutes & Resolutions
    • Management reports
    • Charters & Regulation
  • Information
    • Bidding
    • Recruitment
    • On-going projects undertaken by C47
  • Contacts
C47 > News & Events > News > The Headrace tunnel of Da Nhim Expansion Project is completed ahead of schedule

27/07/2021 by

The Headrace tunnel of Da Nhim Expansion Project is completed ahead of schedule

The Grassroots Acceptance Council inspected and approved the Headrace Tunnel for the Da Nhim Hydropower Plant Expansion project on July 20, 2021. The Acceptance Council agreed to put in into operation on July 21, 2021, six days ahead of schedule, after inspecting the entire length of 4,908.57m from the Intake to the Valve House.

The inspection team

Regarding members of the Grassroots Acceptance Council, there were leaders of Da Nhim Hydropower Plant Expansion Project Management Board (representative of Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company as the Investor), Supervision Consultant (Nippon Koei – PECC3 – Nippon Koei Vietnam), Design Consultant (Power Engineering Construction Joint Stock Company 2), Construction Contractor (Construction Joint Stock Company 47) and Hydro-mechanical Contractor (NARIME – COMA Consortium).

Headrace Tunnel under Da Nhim Hydropower Plant Expansion Project with a total length of 4,908.57m is constructed by TBM (Tunnel Boring Machine) and partly by Drilling and Blasting method. Tunneling work with TBM started on April 1, 2017 with a diameter of 3.9m. On March 23, 2019, when 3,739.51m had been drilled, the tunnel slippage occurred when the TBM passed through a weak geological area. Although the Owner, Consultant and Contractor have made efforts to reinforce and fix the tunnel but the TBM equipment cannot continue to dig the remaining tunnel.

The tunnel section is constructed by TBM at the location of 2,750m

Following approval from the Ministry of Industry and Trade to change the TBM construction plan to drilling and blasting for the remaining 929.05m tunnel, the Construction Contractor resumed work on February 6, 2020, and completed the tunnel on December 14, 2020. After about 6 months of focusing on covering and reinforcing the tunnel at sections with weak geology and overall hygiene, the entire tunnel was ready for acceptance and use on July 20, 2021.

The tunnel section is covered with concrete

Mr. Luu The Bieu – Deputy Director of the Project Management Board – did not hide his emotion when speaking at the acceptance meeting to put the tunnel into use on the same day: “After a difficult time of construction, the Headrace tunnel is ready for water filling. The Da Nhim expansion project is now officially completed. What makes me proud of is the tunnel quality and the construction safety for laborers and equipment”.

To ensure the progress of putting unit H5 of 80 MW under the Da Nhim expansion project into operation in the third quarter of 2021, Da Nhim – Ham Thuan – Da Mi Hydropower Joint Stock Company (DHD) launched an emulation on 16th June 2020. The emulation aims at catching the schedule of filling the tunnel on July 26, 2021 and completing the 72-hour challenge of unit H5 with a capacity of 80MW on August 8, 2021. The completion of the Headrace Tunnel of Da Nhim Hydropower Plant Expansion Project was 6 days ahead of schedule.

The Headrace Tunnel Item under Da Nhim Hydropower Plant Expansion Project is completed ahead of schedule and is considered a crucial basis to put Unit H5 into operation for resource efficiency. Up to now, the inspection of unit H5 after 2.5 years of operation with a capacity of 45MW is being carried out urgently, completing the final items to operate with a capacity of 80MW.

Unit H5 with a capacity of 80MW will increase the total capacity of Da Nhim hydropower plant to 240MW, contributing to additional power sources, especially at off-peak hours for the national power grid. As a multi-purpose hydropower plant, Da Nhim hydroelectricity annually provides more than 1.1 billion kWh for socio-economic development; At the same time, it is an abundant water source for agricultural production in the delta of Ninh Thuan province.

Filed Under: News, News & Events

RELATED POSTS

50-Year Milestone: Transforming into an International EPC Contractor with the Nam Neun 1 Hydropower Project – 124 MW

50-Year Milestone: Transforming into an International EPC Contractor with the Nam Neun 1 Hydropower Project – 124 MW

Half a century has passed, and CC47 has created projects that accompany the nation’s development while building its reputation through responsibility in every undertaking. From the courage to overcome challenges ...
50-year milestone: Construction of the largest-diameter water diversion tunnel at Hoa Binh Hydropower – Vietnam’s “Project of the Century”

50-year milestone: Construction of the largest-diameter water diversion tunnel at Hoa Binh Hydropower – Vietnam’s “Project of the Century”

Over half a century, Construction Joint Stock Company 47 (CC47) has created a trail of pioneering milestones: the first enterprise in Vietnam to own a TBM, opening the era of ...
CC47 General Director attends inauguration ceremony of Unit No. 1 – Hoa Binh Hydropower Expansion Plant

CC47 General Director attends inauguration ceremony of Unit No. 1 – Hoa Binh Hydropower Expansion Plant

Morning of August 19, 2025, in Phu Tho Province, the Inauguration and Grid Connection Ceremony of Unit No. 1 (Hoa Binh Hydropower Plant Expansion Project) took place – one of ...
Chairman of the Board of Directors attends groundbreaking ceremony of Tri An Hydropower Expansion Plant – one of 250 key projects celebrating the 80th anniversary of the August Revolution and National Day on September 2

Chairman of the Board of Directors attends groundbreaking ceremony of Tri An Hydropower Expansion Plant – one of 250 key projects celebrating the 80th anniversary of the August Revolution and National Day on September 2

On the morning of August 19, 2025, in Tri An commune, Dong Nai province, Vietnam Electricity (EVN) together with Power Project Management Board 3 solemnly held the Groundbreaking Ceremony of ...
A 50-year milestone: Vietnam’s first and Southeast Asia’s largest pumped-storage hydropower plant – a strategic piece in the renewable energy landscape

A 50-year milestone: Vietnam’s first and Southeast Asia’s largest pumped-storage hydropower plant – a strategic piece in the renewable energy landscape

On the sun-drenched and windy land of Ninh Thuận (today part of Khánh Hòa province), nestled among towering mountains and tranquil headwater streams, the Bác Ái Pumped Storage Hydropower Plant ...

SUPPLIERS & CONTRACTORS PORTAL

The C47 brand has now become a quality guarantee for world-class buildings. Click on the link to join Supply Chain C47

Submit/RegisterFeedback
0256.3522166
HOTLINE

VIDEO

Công ty Cổ phần Xây dựng 47

Construction Joint Stock Company 47

Kỷ niệm 45 năm thành lập Công ty Cổ phần Xây dựng 47

45th Year Anniversary for establishment of Construction Joint Stock Company 47

Music: Hát về Công ty 47 anh hùng

https://www.xaydung47.vn/wp-content/uploads/2021/03/C47_AH_FIle_Goc.mp3

RECRUITMENT

We’re looking for Assistant to Chairman

Announcement of second recruitment in 2018

Announcement of labor recruitment phase 1 in 2018

Recruitment announcement for the first phase of 2017

Announcement of labor recruitment phase 3 in 2016

COMPANY INFO

  • General Introduction
  • Achievements and Awards
  • Organizational Chart
  • Communist Party & Unions
  • Quality Policy of Company

INVESTOR RELATIONS

  • Information
  • Financial Report
  • Annual Report
  • Announcement
  • Minutes & Resolutions

CONTACTS

Main Office Building C47:
  • No 8 Bien Cuong - Quy Nhon Nam - Gia Lai
  • 0256.3522166 - 0256.3522931
  • c47@xaydung47.vn

C47

Copyright © 2025 Công ty Cổ phần Xây dựng 47
Developed by Vũ Phong Energy Group