| Built in: | Binh Tuong Commune, Tay Son District, Binh Dinh Province, Viet Nam | |
| Dam of length: | 565,01m | |
| Including: – Deep overflow: – Piano spill: – The dam does not overflow: |
72m 301,75m 91,26m |
|
| Height of Crest: | 27,7m | |
| Main amount: | ||
| + Kinds of gravelly soil excavations: | 935.000m3 | |
| + Kinds of gravelly soil cover up: | 165.550m3 | |
| + Kinds of Concrete: | 115.500m3 | |
| Time that started and finished this project : | ||
| + Start: | 22/06/2009 | |
| + Finish: | 27/04/2015 | |